摘要
以整船各分段涂装工时的原始数据为基础,将施工总工期具体至各分段涂装检验工时,结合涂层系统干膜厚度,进行分析、对比,讨论了并行作业、施工区域划分、劳动资源调度等对涂装工时的影响,为设计、生产部门制订涂装生产计划、成本预算、质量控制等提供借鉴。
Abstract
Based on the data of working hours recorded in completion inspection after painting of all sections of the ship,combined with the dry film thickness of the coating system,the painting inspection working hours of each section were analyzed during the total construction period.The influences on painting working hours were discussed such as the parallel-cross-operation,the division of painting area and the scheduling of labor resource.The references were provided for design and production departments to make painting production plan,cost budget and quality controlling.
关键词
船舶涂装;工时;管理
Key words
ship painting;working hours;management
马振伟[1].
基于船舶分段涂装完工检验的涂装工时浅析[J]. 现代涂料与涂装. 2022, 25(11): 37-39
MA Zhen-wei[1].
Brief Analysis of Painting Working Hours Based on Completion Inspection of Ship Section Painting[J]. Modern Paint & Finishing. 2022, 25(11): 37-39
{{custom_sec.title}}
{{custom_sec.title}}
{{custom_sec.content}}